When (first) orbital flight?First integrated flight test occurred April 20, 2023. "The vehicle cleared the pad and beach as Starship climbed to an apogee of ~39 km over the Gulf of Mexico – the highest of any Starship to-date. The vehicle experienced multiple engines out during the flight test, lost altitude, and began to tumble. The flight termination system was commanded on both the booster and ship."
What's happening next? SpaceX has assessed damage to Stage 0 and is implementing fixes and changes including a water deluge/pad protection/"shower head" system. No major repairs to key structures appear to be necessary.
Why no flame diverter/flame trench below the OLM?Musk tweeted on April 21: "3 months ago, we started building a massive water-cooled, steel plate to go under the launch mount. Wasn’t ready in time & we wrongly thought, based on static fire data, that Fondag would make it through 1 launch." Regarding a trench, note that the Starship on the OLM sits 2.5x higher off the ground than the Saturn V sat above the base of its flame trench, and the OLM has 6 exits vs. 2 on the Saturn V trench.
11:56pm- S27 aft end test tank rolled out to Massey’s
12:11am- SQD retracts (Rover2)
1:20am- S29 frost free
1:43am- S27 test tank arrives at Massey’s
1:54am- Grinding on the left chopstick
6:42am- More sparks under the OLM ring to the right of the staircase
6:59am- Sparks to the left of the staircase
7:57am- S25 venting. Looks like the stabilizer pins are engaged
8:20- Lifts were up to both chopsticks, the staircase, the top of the OLM, and to S28 overnight.
10:21am- Chopsticks start lifting S25
10:35am- S27 test tank lifted into the structural test stand at Massey’s.
10:40am- Chopsticks stop
10:41am- SQD swings back over
10:46am- Start swinging over B9
10:53am- Over B9
10:54am- Start lowering
11:27am- Down on top of B9
1:09pm- SQD work platform extended
1:34pm- Worker up on SQD. Looks like they are removing covers on S25’s QD
1:40pm- SQD work platform retracted
1:45pm- Lift has been up at S26 off and on this morning
1:54:55pm- SQD extends
2:17pm- SPMT’s headed to Massey’s. S29 coming back already?
5:00pm- Lift has been up and down to the top of the staircase. The elevator in the tower has been getting a work out today as well going up and down to the SQD level.
5:15pm- Venting at Massey’s. S29 is go for round 2
5:24am- S26’s Lox tank is open with a vent hose run to it
6:16pm- Frost on S29
7:50pm- S29’s lox tank is mostly frosty. Just a small line at the bottom of the methane tank. Lift up to the back side of the OLM and of course, there is one at the top of the staircase
8:19:39pm- S29 depress vent. Never got full frosty
9:48pm- Lift up at S26’s lox tank, back side of the OLM, and to the staircase. More grinding going on inside of the OLM ring to the left of the staircase
10:17pm- S25’s stand is being moved back to the production site/storage area